Transformer Move to Sub Station

Transformer Move-lgThis is a transformer move from a rail site in Sedalia, CO to Daniel’s Park Sub Station.

The load was approximately 157 ft. long, 20 ft.wide and 19 ft. high with a GVW of 432,000 lbs. The move took place over two nights with 18 people participating in various capacities. The transformer was unloaded using two 200 ton Hydraulic Cranes. The cranes set the transformer onto Duffy’s 250 ton Jack and Slide system. The Duffy crew then moved the transformer 200 ft. up a 4% grade to the foundation pad.